Welcome to CDI

CREATIVITY      ACHIEVEMENT      HARMONY      RESPONSIBILITY

Pakistan 7700TPD Clinker Cement Production Line and supporting 12MW WHR (waste heat recovery system) and 24MW CPP (coal fired power plant)

Release Time:09/06/2019                          order:46             Return



Pioneer Cement Company 7000tpd Clinker Cement Production Line with its 12MW Waste Heat Recover system and 24MW Coal-fired Power Plant project locates in Kushab, 350 km away northwest of Lahore, Pakistan. This is a project constructed by CDI on turnkey basis, and with the design capacity of 7000tpd, it can actually maintain operating capacity between 8200tpd-8300tpd.


Go Back

Copyright © Chengdu Design & Research Institute of Building Materials Industry

蜀ICP备13010545号-1  蜀ICP备13010545号   Technical support:LFSOFT