FAC Issued to EPC Project of GOE BENI SUEF 6X6000TPD Clinker Cement Production Line
Release Time:05/28/2019
The Final Acceptance Certificate (FAC) was issued by the Owner to the EPC Project
of GOE Beni Suef 6*6000TPD Clinker Cement Production Line on the 27thof May, 2019.
Signed and executed since June
2016, this EPC Project of GOE Beni Suef 6*6000TPD Clinker Cement Production
Line is not only the biggest cement project constructed simultaneously at the
same time at the same site over the history of world cement industry, but also
the overseas EPC cement project with the shortest contract schedule. With hard
working and elaborate organization, CDI achieved clinker production within 18
months as scheduled in the contract, commenced performance tests on the 7thof March 2018, fulfilled all the performance tests on the 12thof
May 2018, and the Provisional Acceptance Certificate (PAC) was issued by the
Owner on the 27thof May 2018, which announces beginning of the
warranty period.
With entering into the warranty
period, the Ministry of Defense of Egypt established El Wataneya Company for
Cement, Beni Suef to operate the plant. Confronted with the strict requirements
of the new management team, CDI succeeded in maintaining the major KPI indexes
such as equipment running ratio and reliability at the top of the world cement
industry.
Meanwhile,
good effects are also achieved regarding the Owner’s multiple businesses
orientation and energy saving policy, which is highly appreciated by the Owner’s
new management team. And at the last day of the 12-month warranty period, FAC
was issued on the 27thof May 2019, signifying a perfect closure of
the biggest project over the history of world cement industry.