Successful Ignition of Heidelberg’s 5000TPD Clinker Production Line in Togo Turnkey Contracted By CDI
Successful Ignition of Heidelberg’s 5000TPD Clinker Production Line in Togo Turnkey Contracted By CDI
Release Time:09/16/2014
Heidelberg’s 5000TPD clinker production line project in Togo (HTCC), which has been undertaken by CDI on turnkey basis, was ignited successfully by the first shot at 8:00 local time on the 11th of September 2014.
Located at Tabligbo in Togo in western Africa, HTCC project is invested by Heidelberg Cement Group of Germany and constructed by CDI on EPC basis. The project was commenced on the 1st of August 2012 with the contractual time for completion as 29 months, but the factual time for completion is far more advanced than the contract. The quality and the efficiency of the construction has been highly praised by the Owner, the local government, the Chinese Embassy and the Economic and Commercial Counsellor’s Office.